Project
New Pipe rack from Gate of port (56) to jetty ( 1 & 2 ) and to valves station.
Contractor |
Petromaint company |
Value of Contract |
[4 Million LE.] |
Construction Duration |
One Year ( Actual Working Day ) |
Start Day |
--- |
General Scope Of The Project
To improve all the petroleum ports and regulate pipes route, all companies seeking that must be rehabilitee the area around the jetty (1&2) revering that A.P.C will construct a new pipe rack with 3 levels and remove old one which was crowded and very weak lately. It means easy maintenance, more safe, can be put more than 45 lines with different diameters, increase the loadig operation on the port. There are an old pipe rack in east side of petroleum port ceowded very oil. At the same time there are many petroleum comps need a new pipe line in the same erea. Then APC with them agreed to construct a new pipe rack ( shiro pipe rack ) instead of the old one
Notes :
Execution of the project is running with a Satisfactory way.
Two axes are terminated and handed over. Civil and steel works were in parallel. The activities of the third axe are in focus. Civil work will be finished by the end of March 2014 |